Preparations has started for the install of an extra generator in the Brussesl DC facilities First step of the works consists of preparation for the concrete slab. Taking in account the weight of the generator the concrete slab must take on a weight of at least 8 tonnes.

The generator itself has already been delivered waiting to be shipped. The gen set itself is a Caterpillar gen set which has been installed in a container to minimize the noise and protect the machine from the elements.

After the finalization of the concrete slab the container will be moved to his final location.

With the install of a 2nd generator we will have a redundant solution on gen set level besides the connection for a 3rd generator.